Project Management Scenario Report For Vella IT Office Fitouts
Current project status
The project mainly reflects on fitout of a medium rise office building in the suburb of Sydney whose previous project manager “Tony Faultier” left his job suddenly and moved overseas. In order to progress with the project, the company hired a new project manager so that he can be able to communicate properly with the project stakeholders for gathering information about the project progress as well as current status. The estimated budget for the project is around $1.2M and it is assumed that that the fitout of the entire office building will be completed within 4 months. The success of the fitout project must be determined by the management of the company with the help of three components which includes design, budget as well as time.
The paper illustrates the project current status including the cost variances as well as schedule variances of the project. The paper also elaborates the significance of leadership behaviour within the project. Furthermore, the paper helps in providing an overview about the present project team with appropriate recommendations in context to changes within the project policies as well as within the work processes of the project environment.
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
% Work Complete |
Actual Duration |
Actual Cost |
Cost variance |
Schedule variance |
Fitout of medium-rise office building in Sydney |
87.44 days |
Wed 01-03-17 |
Fri 30-06-17 |
$1,200,904.83 |
32% |
27.72 days |
$396,510.61 |
||||
Project plan initiation |
0 days |
Wed 01-03-17 |
Wed 01-03-17 |
$0.00 |
0% |
0 days |
$0.00 |
||||
Project plan |
15.93 days |
Wed 01-03-17 |
Wed 22-03-17 |
$144,348.67 |
32% |
5.23 days |
$48,000.00 |
$96,348.67 |
|||
Project plan development |
2.4 days |
Wed 01-03-17 |
Fri 03-03-17 |
1 |
Project Manager, Project Sponsor, Structural Engineer, Architect, Civil Engineer, Designer |
$30,720.00 |
83% |
2 days |
$25,600.00 |
$5,120.00 |
|
Architect appointment |
8.25 days |
Wed 01-03-17 |
Tue 14-03-17 |
3 |
Project Manager, Civil Engineer, Designer, Project Sponsor |
$66,396.67 |
12% |
2 days |
$9,600.00 |
$56,796.67 |
|
Schematic design |
3.69 days |
Tue 07-03-17 |
Thu 16-03-17 |
4 |
Architect, Civil Engineer, Project Manager, Designer, Developer, Electrician |
$47,232.00 |
27% |
1 day |
$12,800.00 |
$34,432.00 |
|
Consulting proposals |
3.93 days |
Fri 17-03-17 |
Wed 22-03-17 |
5 |
$0.00 |
0% |
1 day |
$0.00 |
$0.00 |
||
Documentation and design |
87.44 days |
Wed 01-03-17 |
Fri 30-06-17 |
$696,493.50 |
49% |
49.97 days |
$348,510.61 |
$3,47,982.89 |
|||
Tender documentation |
2 days |
Mon 20-03-17 |
Tue 21-03-17 |
6 |
Project Manager, Project Sponsor, Designer, Developer, Electrician, Architect, Civil Engineer, Site investigator, Structural Engineer |
$16,000.00 |
100% |
2 days |
$16,000.00 |
$0.00 |
|
Submission of documentation for approval |
3 days |
Wed 22-03-17 |
Fri 24-03-17 |
8 |
$24,000.00 |
33% |
1 day |
$8,000.00 |
$16,000.00 |
||
Designing services |
3.5 days |
Fri 17-03-17 |
Tue 28-03-17 |
9 |
Architect, Civil Engineer, Designer, Project Manager, Developer, Electrician, Project Sponsor, Site investigator, Structural Engineer |
$89,258.00 |
57% |
2 days |
$50,961.06 |
$38,296.94 |
|
Documentation completion |
2 days |
Wed 22-03-17 |
Wed 29-03-17 |
10 |
Project Manager, Project Sponsor, Architect, Civil Engineer, Designer, Developer |
$23,214.00 |
50% |
1 day |
$11,607.00 |
$11,607.00 |
|
Ground floor |
5 days |
Wed 01-03-17 |
Tue 07-03-17 |
$118,960.00 |
75% |
3.96 days |
$89,528.80 |
$29,432 |
|||
Development of telecom infrastructure, electrical works, plumbing as well as furniture for ground floor |
4.5 days |
Wed 01-03-17 |
Tue 07-03-17 |
3 |
Architect, Civil Engineer, Designer, Structural Engineer, Developer, Electrician, Project Manager, Project Sponsor |
$118,960.00 |
75% |
3.56 days |
$89,528.80 |
$29,432 |
|
First floor |
73.42 days |
Wed 01-03-17 |
Mon 12-06-17 |
$24,850.00 |
25% |
11.08 days |
$6,241.67 |
$18,609 |
|||
Development of telecom infrastructure, electrical works, plumbing as well as furniture for first floor |
4.9 days |
Wed 01-03-17 |
Mon 12-06-17 |
3 |
Architect, Civil Engineer, Designer, Project Manager, Structural Engineer |
$24,850.00 |
25% |
0.74 days |
$6,241.67 |
$18,609 |
|
Second floor |
37.97 days |
Wed 01-03-17 |
Fri 21-04-17 |
$150,731.50 |
25% |
13.6 days |
$40,172.08 |
$110,579 |
|||
Development of telecom infrastructure, electrical works, plumbing as well as furniture for first floor |
6.7 days |
Wed 01-03-17 |
Fri 21-04-17 |
3 |
Designer, Project Manager, Structural Engineer, Architect, Civil Engineer, Developer, Electrician, Project Sponsor, Site investigator |
$150,731.50 |
25% |
2.4 days |
$40,172.08 |
$110,579 |
|
Top floor |
14 days |
Mon 12-06-17 |
Fri 30-06-17 |
$249,480.00 |
50% |
10.5 days |
$126,000.00 |
$123,480 |
|||
Development of telecom infrastructure, electrical works, plumbing as well as furniture for top floor |
14 days |
Mon 12-06-17 |
Fri 30-06-17 |
3 |
Architect, Civil Engineer, Designer, Developer, Electrician, Project Manager, Project Sponsor, Site investigator, Structural Engineer |
$249,480.00 |
50% |
10.5 days |
$126,000.00 |
$123,480 |
|
Construction phase |
25.7 days |
Fri 03-03-17 |
Mon 10-04-17 |
$307,118.67 |
0% |
0 days |
$0.00 |
$307,118.67 |
25.7 days |
||
Developing approval from the owner |
2 days |
Fri 03-03-17 |
Tue 07-03-17 |
3 |
Architect, Civil Engineer, Designer |
$17,166.67 |
0% |
0 days |
$0.00 |
$17,166.67 |
2 days |
Creation of project procurement |
5.4 days |
Tue 07-03-17 |
Mon 20-03-17 |
21 |
Civil Engineer, Designer, Project Manager, Site investigator, Developer, Electrician, Project Sponsor |
$83,752.00 |
0% |
0 days |
$0.00 |
$83,752.00 |
5.4 days |
Consultation with head contract |
5.3 days |
Mon 20-03-17 |
Mon 27-03-17 |
22 |
Architect, Civil Engineer, Site investigator, Structural Engineer |
$72,400.00 |
0% |
0 days |
$0.00 |
$72,400.00 |
5.3 days |
Installation of furniture |
5 days |
Mon 27-03-17 |
Mon 03-04-17 |
23 |
Architect, Civil Engineer, Designer |
$60,000.00 |
0% |
0 days |
$0.00 |
$60,000.00 |
5 days |
Completion of practical work |
4.5 days |
Mon 03-04-17 |
Mon 10-04-17 |
24 |
Civil Engineer, Designer, Site investigator, Structural Engineer |
$73,800.00 |
0% |
0 days |
$0.00 |
$73,800.00 |
4.5 days |
Closure phase of the project |
22.33 days |
Fri 03-03-17 |
Tue 04-04-17 |
$52,944.00 |
0% |
0 days |
$0.00 |
$52,944.00 |
22.33 days |
||
Creation of project draft |
4.83 days |
Fri 03-03-17 |
Tue 04-04-17 |
3 |
Civil Engineer, Project Manager, Project Sponsor |
$23,184.00 |
0% |
0 days |
$0.00 |
$23,184.00 |
4.83 days |
Creation of final report for the project |
6.2 days |
Tue 14-03-17 |
Thu 30-03-17 |
Project Manager |
$29,760.00 |
0% |
0 days |
$0.00 |
$29,760.00 |
6.2 days |
The additional information that is important to be sourced for the new project manager so that detailed status of the project can be produced is illustrated below:
Information about project limitations: It is also important to have proper information on the limitations of the project so that while progressing with the project, the new project manager will take care of the limitations so that it may not obstruct the project progress. In addition to this, it is identified that proper information as well as data on the limitations of the project assists them in making the project successful.
About project goal: It is identified that information about the goal of the project is necessary to source so that the project managers will be able to complete the project successfully within the estimated time and budget as per the objectives or goal.
Project risks: It is very much important to have proper information about the risks to the new project manager so that they can be able to implement proper strategies as well as steps that are helpful in mitigating the challenges as well as issues. In addition to this, it is analyzed that if the new project manager is able to take proper steps then the project will be executed successfully within the estimated budget and time.
Task Name
According to the organizational zoo model, it is identified that the leadership tactics that is utilized by Tony faultier is poor. The model states that a leader is an individual who must have huge number of followers who are always eager to help them as they got inspired by the leadership qualities as well as style of managing various work processes. However, it is identified that Tony Faultier is one of the leader who is considered as belligerent and as a result the team members of the project see him as very much lazy as well as impatient. In addition to this, Tony faultier is quite intolerant towards others as he has an autocratic nature which enhances his unwillingness to hear others advice or perspective of thought which states that Tony Faultier is one of the poor leader. Furthermore, the improper performance of Tony faultier suggests that as per the organizational zoo model that he is not a good or real leader who lacks proper leadership style.
It is found that for the recruitment of the new project manager, it is very much necessary to recruit based on some of the leadership behaviour that are mainly illustrated below:
Demonstration of truth: It is quite important for the project manager to have proper information about the project issues as well as risks in order to take proper decision. Real project managers generally demand reality from its team members so that they can get information about each step that is taken in the project. In addition to this, it is analyzed that hiding risks as well as negative results of the project from the project manager may further create obstructions for the project.
Courage demonstration: The leader must have the courage to share both positive as well as negative outcome with the stakeholders of the project so that they can be able to work together for making the project successful.
Demonstration of drive for results: It is necessary for the project manager to have proper leadership qualities or characteristics that helps them in achieving desired outcome within the project.
The present team environment is found to be improper as there is communication gap between the project managers as well as other team members of the project. It is identified that the risks which are mainly related to the project are only known to the few project stakeholders which generally reflects that if the information about the risks are not properly communicated then the progress of the project will get obstructed.
Duration
The recommendations of the project are as follows:
Proper communication: Proper communication between the team members as well as project manager is very much important for making the project successful. Appropriate communication with the project team members generally assist in mitigating challenges as well as risks which are mainly related with the project.
Clarification of roles: In order to build proper environment within the company, it is very much important that the stakeholders of the project must know their roles properly so that they can work properly which further can be helpful for bringing efficiency as well as flexibility with the project work.
Trusting team members: It is necessary to create proper trust between various team members of the project for building proper team environment within the project. In addition to this, it is analyzed that team members of the project must be remain competent as well as responsible towards work.
I have identified in the project of fitout medium size office building in Sydney that proper leadership behaviour must be present with the project manager so that they can be able to manage as well as complete the project effectively within the estimated budget as well as time. After proper research o organization zoo model, I have analyzed that the project leaders needs to be responsible as hardworking for getting achieving proper outcome from the project. Before getting involved with the project, I have found that it is very much necessary to have proper information about projects, risks, limitations, objectives, project stakeholders and more. This information helps in leading project managers in the right direction. From proper analysis I have understand the significance of team environment on the project. Therefore in order to improve the outcome of the project it is necessary to make some changes within the work environment of the project. The most important change that is needed is to remove the communication gap that is present within the project manager as well as project team members. Proper friendly relation helps the team members in working effectively within the project. In addition to this, it is identified that before the recruitment of project managers, they must be tested against various leadership characteristics so that it can be ensured that the recruited project managers will manage the project effectively.
Conclusion
It can be concluded from the entire project that in order to continue with the project of fitout medium rise office building in the suburb of Sydney, a new project manager must be hired based on some of the specific leadership behavioural characteristics. The project manager must have the qualities that are needed within a leader as per the Zoo organizational behaviour. The paper also analyzes the present team environment in order to identify the problem so that proper recommendation must be provided in order to make changes within the work environment of the project.
Aga, D. A., Noorderhaven, N., & Vallejo, B. (2016). Transformational leadership and project success: The mediating role of team-building. International Journal of Project Management, 34(5), 806-818.
Be?ikci, U., Bilge, Ü., & Ulusoy, G. (2015). Multi-mode resource constrained multi-project scheduling and resource portfolio problem. European Journal of Operational Research, 240(1), 22-31.
Browne, W., Dreitlein, S., Manzoni, J., & Mere, A. (2016). Two key success factors for global project team leadership: Communications and human resource management. Journal of Information Technology and Economic Development, 7(2), 40.
Harms, R. (2015). Self-regulated learning, team learning and project performance in entrepreneurship education: Learning in a lean startup environment. Technological forecasting and social change, 100, 21-28.
Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.
Iluz, M., Moser, B., & Shtub, A. (2015). Shared Awareness among Project Team Members through Role-based Simulation during Planning–A Comparative Study. Procedia Computer Science, 44, 295-304.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kim, D., & Moon, T. (2016). The Study on Transactive Memory Systems on Team Performance and the Moderating Effect of Collective Mind. Advanced Science and Technology Letters (179-184) Vol, 126.
Leonard, A. (2014). Role and impact of social relationships and networks in a software project team environment–a conceptual framework. Journal of Project, Program & Portfolio Management, 4(2), 1-19.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Tyssen, A. K., Wald, A., & Heidenreich, S. (2014). Leadership in the context of temporary organizations: A study on the effects of transactional and transformational leadership on followers’ commitment in projects. Journal of Leadership & Organizational Studies, 21(4), 376-393.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Top-quality papers guaranteed
100% original papers
We sell only unique pieces of writing completed according to your demands.
Confidential service
We use security encryption to keep your personal data protected.
Money-back guarantee
We can give your money back if something goes wrong with your order.
Enjoy the free features we offer to everyone
-
Title page
Get a free title page formatted according to the specifics of your particular style.
-
Custom formatting
Request us to use APA, MLA, Harvard, Chicago, or any other style for your essay.
-
Bibliography page
Don’t pay extra for a list of references that perfectly fits your academic needs.
-
24/7 support assistance
Ask us a question anytime you need to—we don’t charge extra for supporting you!
Calculate how much your essay costs
What we are popular for
- English 101
- History
- Business Studies
- Management
- Literature
- Composition
- Psychology
- Philosophy
- Marketing
- Economics